2018

Power Plant Turów project progress

In October 2018 SINKOS continues the construction of 6 steel tanks for Power Plant Turów in Bogatynia. The material is stainless steel 316L and P235GH. Capacity varies from 150m3 up to 3000m3.Two tanks will be covered inside with rubber lining. The project is being performed in formula “Design and build”. The all tanks will be a part of desulphurization system. 

Montage of industrial steel platforms

In October 2018 SINKOS started final assembly of stairs and platforms in sulphur acid branch of Chemical Plant ZCH Police. Total weight is over 40 T, completion of task is planned on December. 

 

Completed pipelines and ducts

In October 2018 SINKOS has completed construction works of stainless steel ducts for fumes. The ducts with oval- and rectangular shape will be connected by flanges on site in south France. The ducts will be mounted on sludge dryer delivered on site by ISNKOS in advance this year. 

 

Modernization of fuel storage tanks

In September 2018 SINKOS has started a modernization of storage tanks 5000m3 for fuel. The scope of works comprise installation of second bottom within the tanks. The space between both partitions will be equipped in detection device vapours. These works are determined by the technical code. 

 

Ducts in stainless steel

In September 2018 SINKOS has started production of stainless steel ducts for customer from Germany.  The oval- and rectangular shape of ducts will be connected by flanges. The final installation on site is planned on end of October. 

 

New sludge dryer for France

In September 2018 SINKOS has started construction of new sludge dryer for a customer from France. The  dryer will be made in stainless steel AIS 316L acc. to Danish technology. The unit will be equipped in belts drive, heating system and steering devices delivered from Danmark. Total weight of the dryer: over 22 T, length: over 18 m. 

Modernization of production plant Bridgestone

In August 2018 SINKOS has completed modernization of production plant Bridgestone in Stargard. The production unit for glue for rubber have been equipped in electrical cables for steering of new valves and in new pipelines in steel 316L. The tanks for glue have been equipped in additional nozzles for filters and gauges. 

 

Power Plant Turów extension progress

In April 2018 SINKOS continue the construction of 6 steel tanks for Power Plant Turów in Bogatynia. Part of tanks will be constructed in stainless steel 316L. Capacity varies from 150m3 up to 3000m3. Two objects will be cladded inside with a rubber lining. The project in being performed in formula “Design and build”. The all tanks will be a part of desulphurization system within the power plant. 

 

Successful bid for industrial steel platforms

In April 2018 SINKOS won a tender bid and started the manufacture of industrial system of platforms and stairs for Chemical Works ZCH Police. Total weight is over 80 T, assembly in the workshop is planned for June. 

 

3 tanks for chemical plant

In March 2018 SINKOS has started production of three tanks for chemical plant in Kedzierzyn-Kozle. Capacity of tanka: 1000m3 and 2x 500m3. Final assembly is foreseen in May/June. 

 

Completion of sludge dryer for France

In March 2018 SINKOS has completed and sent to the site in south France the  sludge dryer made in stainless steel AIS 316L. The unit has been equipped in drive and steering devices delivered by Danish client. Total weight of the dryer: over 24 T, length: over 21 m. 

Delivery of steel stairs and platforms

In March 2018 SINKOS has completed construction and sent to the building site in Czech Republic a system of steel stairs and platforms. The structure will be fitted on existing reactors of a paper mill. The engineering design was part of the order. 

 

Completion of two tanks 500m3

In February  2018 SINKOS has completed electrical furnishings in two steel tanks 500m3 for demineralized water in Power Plant Opole. The tanks have been equipped in electrical heating cables mounted on tank’s shell. Now they are ready for final commitment and handover to customer. 

 

2017

Building permission for a paint production plant

In December 2017 SINKOS has received from local authorities  a building permit for construction of extended paint production plant Sherwin-Williams. The new part of factory consists of unloading station, tank-farm with eight tanks and pipelines together with control system network, storage house and heating-room. 

 

Start of new tankfarm in Turów

In November 2017 SINKOS has started construction of first tank in Power Plant Turów. The new tank capacity 3000m3 will be the first of six others to be constructed by mid 2018. The new tank-farm consists of six objects capacity from 150 up to 3000m3. Two of the tanks will be additionally rubbered inside and insulated. The all tanks will be part of desulphurization system within the plant. 

 

Start of manufacture of a sludge dryer

In November 2017 SINKOS started the manufacture of a sludge dryer for a French customer. The grade of steel is 316L. This unit will be produced upon Danish engineering design and is a prototype in its branch. 

 

Completed installation of steel pipelines and ducts

In November 2017 SINKOS has completed installation works in Chemical Plant in ZCH Police. The task consisted of assembly of stainless steel pipes and ducts on height up to 40 m above the ground. These fittings are a part of desulphurisation system within the factory. 

 

Stainless steel skid frame

In October 2017 SINKOS has completed the production of steel skid frame for Norwegian customer. The structure will be equipped with piping, valves and gauge devices for offshore industry. Material – AISI 316L. 

 

Completion of rotary dryer device

In October 2017 SINKOS has completed construction of a rotary dryer device for Chemical Plant ZCH Police. The grade of stainless steel is AISI 321. 

 

Tank for phosphorus acid

In October  2017 SINKOS has completed construction of a steel tank for phosphorus acid for Chemical Works ZCH Police. The tank in covered inside with a rubber layer 5mm. The bottom is padded inside with acid-resistant bricks. The tank is a part of new output installation. 

Extension of paint production plant, engineering completion

In August 2017 SINKOS has completed the  engineering design for extension of a paint production plant near Poznan. The new part of factory consists of unloading station, tank-farm with pipelines and control instrumentation network, storage house and heating-room. 

 

New contract for tanks for Power Plant

In August 2017 SINKOS has signed a contract for engineering design and construction of number of tanks as a part of desulphurization system of Power Plant Turów. The new tank-farm consists of six units capacity from 150 up to 3000m3. Part of the tanks will be rubbered inside and insulated. The steel grade is stainless steel 316L (40%) and carbon steel (60%). 

 

Start of pipeline construction

In August 2017 SINKOS has started construction of pipeline network in chemical plant Grupa Azoty SA in Police. The task is being performed in “design and build” formula. Total length of the system exceeds 3000 m, the diameter of pipes varies from DN80 up to DN250, the stainless  steel grade is 304 and 316, and 10% is a special alloy steel. The completion of works is planned for December 2017. 

 

Offshore steel structures

In August SINKOS completed the next set of steel frames for offshore project. This is a part of special rescue Davits system to be mounted on sea platforms. The total weight of the structures exceeded 500 T. 

 

Start of assembly of two 500m3 tanks for demineralized water

In July2017 SINKOS started the assembly of two storage tanks for demineralized water on the buiding site In Power Plant Opole. The tanks In stainless steel 316L will have the heating system and thermal insulation. They will serve as a part of desulphurization  processing site. 

 

Completed installation in chemical plant 3M in Wroclaw

In July 2017 SINKOS has completed installation works in 3M Manufacturing in Wroclaw. The task consisted of stainless steel tanks and pipelines, pumps and steering&control automation system. These branch components belonged also to the engineering design completed by Sinkos. 

Fuel tank 2000m3 for ORLEN

In June 2017 SINKOS has completed the  steel shell of fuel storage tank 2000m3 for ORLEN. The final assembly on the building site will be performed in August 2017. 

Tank delivery to 3M Manufacturing Poland

In April 2017 SINKOS has sent a stainless steel tank for new tank-farm for chemicals and alkyd resins in Polish subsidiary of 3M Manufacturing in Wroclaw. The tank consists of double bottoms and shells. It was fully designed by the manufacturer engineers of Sinkos. The design comprises storage tanks with pipelines, pumps and control devices. 

 

Offshore steel structures

In March SINKOS continues the manufacture of steel frames for offshore project. This is a part of special rescue Davits system to be mounted on sea platforms.

 

Steel beams for offshore industry

In March 2017 SINKOS has signed a contract for production of 350 T of steel beams for offshore industry. The beams will be destined for disassembly works of existing old offshore platform on North Sea.

 

Secondary steel structure

In February 2017 SINKOS has completed the secondary steel structure for a tankfarm in Germany. The steel platforms and gratings will be assembled on site in April.

 

Fume ducts

In March 2017 SINKOS has been assembling the steel fume ducts for Chemical Plant Grupa Azoty SA. The ducts in P335GH are a part of Desulphurization System EC-2.

 

Completion of Emergency Tank 3000m3

In January 2017 has completed the Emergency Storage Tank 3000 m3 for Desulphurisation System in Chemical Works Police.

 

Tankfarm engineering

In January 2017 SINKOS has signed an contract for engineering design of  a tankfarm for chemicals and alkyd resins for a Polish chemical company. The design comprises storage tanks with pipelines, pumps and control devices.

 

2016

Offshore steel structures

In December 2016 SINKOS continues the construction of steel frames as Davits structures for offshore project. They are part of rescue Davits system to be mounted on sea platforms.

Extension of paint production plant

In November 2016 SINKOS has signed a contract for engineering design of extension of a paint production plant near Poznan. The new part of factory consists of unloading station, tank-farm with piping and instrumentation, storage house, roads and carport.

 

Completion of delivery of tanks

In November 2016 SINKOS has delivered two last steel tanks for desulphurization system of Power Plant Opole. Because of big dimensions the tanks have been delivered on a barge along Odra river. The whole scope of the project comprised delivery of 16 different tanks in total.

Completion of fuel tanks in Gdynia

In November 2016 SNKOS has completed construction of steel tanks 750 m3 for fuel in Gdynia, north Poland. The accomplishment works comprised both surface treatment and thermal insulation.

 

Desulphurisationplant fume ducts

In last 3 months of 2016 SINKOS has continued theconstruction of fume ducts for Chemical Plant GrupaAzoty SA. The ducts will be a part of Desulphurization System EC-2. The ductsare being produced in carbon steel S355.

 

Stainless steel tanks

In October SINKOS has completed and delivered a stainless steel tank for client from Norway. The tank is for storing potable water as a part of water-treating station.

Offshore structures

In September 2016 SINKOS has begun the erection of steel frames as Davits launchers for offshore project. They are part of rescue Davits lauchers to be mounted on sea platforms. Completion of the project is planned for February 2017.

Tanks for Power Plant Opole

In September SINKOS has delivered next part of steel tanks for extension of the Power Plant Opole. They are a part of Desulphurisation System for Power Plant. The last delivery is planned for November.

Production of steel structures

In August SINKOS has concluded the production of number of orders for manufacture of steel structures for clients from Germany. The scope of work comprised the roof-platforms with railings, tank stairs and steel foundations under tankfarm.

Pipelines for Grupa Azoty

In August 2016 SNKOS won a tender bid for design and construction of steel pipelines for Desulphurisation System for GrupaAzoty SA. The time schedule for final production and assembly of the pipelines is Dezember 2016.

Order for construction of fume ducts

In July 2016 SINKOS has got an order for construction of fume ducts for Chemical Plant GrupaAzoty SA. The ducts will be a part of Desulphurization System EC-2. The ducts will be delivered by December 2016.